By LCN Business Desk
Prime Minister Mark Phillips confirmed on Wednesday that the government has approved more than US$100M more for Lindsayca. The company is building Guyana's gas-to-energy plant at Wales.
Asked how much, he told Kaieteur News he could not recall it.
What did the Prime Minister say?
That the money was approved, and that the company got what it asked for.
Speaking during the sitting of the National Assembly and then to Kaieteur News, Phillips confirmed the approval in terms: "Yes we had meetings and we approved additional financing."
On the figure he said: "We approved additional financing in the sense that they don't have any problems to finish the work as per schedule. The amount, I can't recall the amount but I will share the information with you later. Everything that they asked for they got."
That last sentence is the one a contractor reads. It describes a request granted in full, by a government that has not stated its size.
What was the plant contracted at?
US$759M, for delivery by the end of 2024.
The original contract value is US$759M, Kaieteur News reported. Completion was scheduled for the end of 2024, and the plant has not delivered power.
The additional financing is not the first sum to land on top of it. The Office of the Prime Minister settled two disputes with Lindsayca Guyana Inc on 14 May 2026, raising the contract 12.8 per cent, which Kaieteur News reported as a win of approximately US$97M. Taken with the approval confirmed on Wednesday, at least US$197M has been added to a US$759M contract, and the newer of the two figures has no stated value at all.
That May settlement is also where the December date comes from. The contractor committed to first power by the end of 2026, and the government kept the right to reinstate penalties if the date is missed.
Who else had been pressing for it?
The United States Embassy, according to Kaieteur's earlier reporting.
Kaieteur News reported that the US Embassy in Georgetown was allegedly pressing for a further US$102 million to finish the delayed project. President Irfaan Ali confirmed in September that the company was seeking more. He said then that no discussions were under way.
Two months later the Prime Minister confirms the approval. Between those statements the position moved from a request without discussions to an approval without a number.
Is the December deadline still standing?
The minister responsible says it is.
Deodat Indar, Minister of Public Utilities and Aviation, told Kaieteur News on Wednesday that the commitment is unchanged: "We have held them to task. The original commitment is that you have to deliver one of the turbines by December. We are not shifting from that, period. We are not. They are working. They have the full staff complement, they are working."
In August the company committed to produce 57MW by December 2026. When asked whether Lindsayca remained on track for that timeline, the minister gave no definitive answer, Kaieteur reported.
The penalty right the government retained in May is what stands behind that date. A deadline that can be enforced is a different instrument from one that cannot. That is why the December turbine matters more than the megawatt figure attached to it.
Why does the unstated figure matter commercially?
Because the plant is a cost line that reaches the tariff, and the line is moving.
Wales is where the gas-to-energy programme lands. A business paying for electricity in Guyana is the eventual counterparty to what the plant costs. Each sum added to the contract is a sum to be recovered, and at present one of them is a number the government has confirmed approving and not confirmed.
The saving was the reason given for building it. The Prime Minister has said the promised fifty per cent cut to bills waits on the plant running at full capacity. That puts the tariff effect behind a completion date that has already moved once. In the meantime the grid it is meant to relieve has gone dark in Georgetown five days after the utility said it had enough power, and four of Guyana's ten regions lost power on the morning of 30 October.
The plant is a different contract from the pipeline that feeds it. The line was built by ExxonMobil and is repaid by Guyana. The gas-to-energy task force head put that at US$55 million a year for twenty years. The principal behind it has never been finally confirmed either. The plant and the pipeline are separate contracts with separate counterparties, and neither carries a settled final cost on the public record.
The entities
- Lindsayca is the contractor building the gas-to-energy plant at Wales. - Mark Phillips is Guyana's Prime Minister and confirmed the additional financing. - Deodat Indar is Minister of Public Utilities and Aviation. - Irfaan Ali is Guyana's President and said in September that the company was seeking additional resources. - Wales is the West Bank Demerara site of the gas-to-energy plant. - ExxonMobil built the pipeline that feeds the plant, which is a separate contract. - Kaieteur News reported the confirmation and the figures. - Lindsayca Guyana Inc is the party to the two disputes settled on 14 May 2026.
What the title card says
- Headline: Guyana approved more than US$100M more for the Wales plant, and the Prime Minister who approved it could not state the sum. - Additional financing approved: more than US$100M. - Sum stated by the Prime Minister: none. - Original contract value: US$759M. - Won by Lindsayca in an earlier dispute: approximately US$97M. - Sum the US Embassy was reported to be pressing for: US$102 million. - Original completion date: end of 2024. - Commitment for December 2026: 57MW.
Frequently Asked Questions
How much additional financing did Guyana approve for Lindsayca?
More than US$100M, confirmed by Prime Minister Mark Phillips. He told Kaieteur News he could not recall the exact amount and would share it later.
What was the original contract worth?
US$759M, with completion originally scheduled for the end of 2024.
Has Lindsayca received other money beyond the contract?
Yes. It won a dispute against the government for approximately US$97M, confirmed by the Prime Minister's Office in May 2026.
What was the United States Embassy's role?
Kaieteur News reported that the Embassy in Georgetown was allegedly pressing the government to pay Lindsayca an additional US$102 million to complete the delayed project.
Is the Wales plant still due to deliver power in December?
Minister Deodat Indar said the commitment to deliver one turbine by December stands. The company committed in August to produce 57MW by December 2026.
Is this the same contract as the gas pipeline?
No. Lindsayca builds the plant at Wales. The pipeline feeding it was built by ExxonMobil under a separate arrangement repaid by Guyana.