# Trinidad's Works Minister Put a TT$112 Billion Figure on the Blueprint. Its Own Portal Names Ten of the 129 Projects and Never States It.
- URL: https://www.lacaribenanews.com/trinidad-blueprint-112-billion-portal-ten-projects-couva-2026/
- Published: 2026-11-24T19:10:42.000Z
- Updated: 2026-11-24T19:10:44.000Z
- Description: Minister of Works Jearlean John told the Couva Point Lisas Chamber on 22 November that the Revitalisation Blueprint is worth $112 billion across 129 projects. The figure appears nowhere on the programme portal, which names ten projects. The one working entry point there is a UDeCOTT eTender log-in.
- Author: Theon Alleyne
- Tags: Beat: economics, MSME: direct

**Quick summary:** Minister of Works Jearlean John told the Couva Point Lisas Chamber on 22 November that the Revitalisation Blueprint is worth $112 billion across 13 development nodes and 129 projects. The figure appears nowhere on the programme portal, which names ten projects. The one working entry point there is a UDeCOTT eTender log-in.

## What did the minister tell Couva businesses?

On 22 November, Minister of Works and Infrastructure Jearlean John put a figure on the Revitalisation Blueprint that the Government has not published: $112 billion, across 13 development nodes and 129 projects over ten years.

She gave it at the Couva Point Lisas Chamber of Commerce end-of-year function. The chamber sits beside the country's largest industrial estate. [She challenged the firms there to improve their infrastructure, productivity and competitiveness](http://www.guardian.co.tt/news/john-tells-couva-businesses-to-prepare-for-112b-investment-drive-6.2.2716422.ccf167190a?ref=lacaribenanews.com) so they could take the work when it comes.

"We have spent enough time talking about what Couva could and should become," she said. "Just look around us. We already have one of the most important industrial centres in T&T."

Then the instruction, in her own words to the room.

**"Do not miss future business opportunities because you failed to prepare."**

## Where does the TT$112 billion figure come from?

From her, at that dinner.

It is a large number and it is new to the public record this week. It is also carried by one newsroom. Guardian Media reported it, and Guardian Media owns both the Trinidad Guardian and CNC3, so that is one source rather than two.

The independent account of the launch does not carry it. The Trinidad Express covered the unveiling at the Diplomatic Centre in November 2025 and [described a multibillion-dollar vision without naming a total](https://trinidadexpress.com/news/local/governments-billion-dollar-dream-unveiled/article%5Fe7984f26-c397-4b4f-804a-c822e6f26ec4.html?ref=lacaribenanews.com).

Neither does the Government.

At the rate the same reporting uses for the one project under way, $112 billion is about US$16.5 billion. That is the scale a Couva firm is being asked to prepare for, on one minister's arithmetic.

Announced investment has now been described four ways in this market inside a year. A total at a chamber dinner is the newest. [In Port of Spain on 17 November a United States Assistant Secretary of State said American investors were ready to make five billion dollars of projects, which the Embassy called projects companies came to explore and the Government called potential investment subject to due diligence](https://www.lacaribenanews.com/trinidad-five-billion-pipeline-segura-kern-due-diligence-modal-2026/). None of the four is a contract.

## What does the Blueprint's own portal give a supplier?

Less than the dinner did.

The programme runs its own investor site at [ttglobalhub.gov.tt](https://ttglobalhub.gov.tt/?ref=lacaribenanews.com), branded the Trinidad and Tobago Global Logistical Hub. We read the home page, two project pages and the two pages its buttons point to on 24 November. In the text a visitor can see, the site never states a value, never says 129 projects, and never uses the phrase development node.

It names ten projects, and these are they:

\- Port of Spain Innovation and Development Hub - San Fernando, billed as the Southern Beacon of Transformation - Isla Carrera Resort - The Golden Grove Commons - The National Security Complex - The Tamana Consolidation Prison Campus - Chaguaramas Border Security Upgrade - Central Government Campus Plaza - South Eastern Energy Belt, covering the San Fernando to Mayaro highway and the Port of Galeota expansion - The South West Security Hub

Four of the ten are prisons, security complexes or border upgrades. A firm reading the site for commercial work is reading a list that is mostly state security building.

Two of its invitations go nowhere. The page offers "Want to Work with Us? Send Brief" and "Want to Stock Up? Go to Shop". Both links return a 404\. The page also asks a visitor with a project to write to info@website.com, which is the address the website template shipped with.

One link works, and it is the one that matters. Expression Of Interest in the main menu opens UDeCOTT's eTender system. It is a log-in wall. A firm that has never registered has to create an account there first, and the page files it under store. The footer reads TSTT © 2015.

That is the door. Nothing on the portal says so in words.

## What is the one dated gate she gave?

January, for one set of roads.

She said tenders were expected to be pursued around January, with works possibly starting between late January and February, subject to procurement. That applies to a named list of Chaguanas congestion works: overpasses at Monroe Road, Price Plaza, Brentwood, Mulchan Seuchan Road and Chase Village.

It is the only forward date in her remarks with a procurement step attached. A contractor can act on it. Everything else she described is either under way or under negotiation.

She gave one other date, and it is the one the whole programme rests on. Additional natural gas is expected to reach the national grid from the second quarter of 2027\. Gas is the reason the Blueprint exists. [Utilisation fell from 3.5 billion cubic feet a day in 2015 to 2.4 billion in 2024](https://www.lacaribenanews.com/trinidad-data-centres-golconda-gas-allocation-2026/). On 20 November, at the CARICOM governors' panel in Belize, [the Governor of the Central Bank urged diversification as the region's top priority](https://www.lacaribenanews.com/trinidad-howai-energy-paradox-diversification-migration-2026/). A supplier weighing plant and hiring against this pipeline is weighing it against that second quarter.

She also asked the firms to take on young people through mentorship, technical exposure and apprenticeships. "We cannot be surrounded by industry and have young people who cannot see a pathway into it," she said.

The caution sits in the last three words. This programme has missed a window before. [In February the same minister said contract awards would begin in May or June, and the first sod was not turned until 20 November](https://www.lacaribenanews.com/trinidad-revitalisation-blueprint-one-sod-turned-50919-jobs-2026/), on a privately financed development.

## What about the steel plant she named?

That one is real, independently reported, and it started in August.

John said negotiations were under way involving state-owned Plipdeco and Ibis Steel Company of Trinidad and Tobago Limited over the former ArcelorMittal iron and steel plant at Point Lisas. She said the operation could also produce vanadium, and that Russia and China together account for an estimated 80 to 85 per cent of world production of it.

Then she went further. "So can you imagine T&T would be producing, in effect, potentially 50 per cent of the supply to the US." That is her projection, not a measurement, and the plant is not yet making anything.

The hard numbers are on the record elsewhere. The Trinidad Express reported in August that [the plant restarts on a US$250 million investment by Pinnacle Steel and Vanadium, with 350 jobs during refurbishment and 500 once production begins](https://trinidadexpress.com/business/local/pt-lisas-steel-plant-set-for-revival-with-vanadium-as-new-prize/article%5Fc5ef8dff-de3b-4e1a-9a8b-0104920a3f94.html?ref=lacaribenanews.com). Chief executive Edwin Bennett announced it at an opening ceremony on Mediterranean Drive, in Couva. The company said total investment could reach US$750 million. It is targeting first production by the end of 2027.

Ibis Steel is the local vehicle. [It is a subsidiary of Pinnacle Steel and Vanadium, and refurbishment began on 10 August](https://www.lacaribenanews.com/point-lisas-steel-restart-ibis-pinnacle-gas-supply-2026/). Two names, one plant.

Her gas date matters most here, and she may not have meant it to.

That plant runs on gas-based direct reduction. When refurbishment began, no gas supply agreement had been announced, and gas terms are what killed the previous restart. She has now given a date for the extra gas: the second quarter of 2027\. The plant is targeting first production by the end of that year.

She did not say where the gas comes from. Trinidad's nearest untapped volume sits in a field it shares with Venezuela, and [Caracas licensed its half of Loran in August to a BP-led group in which ADNOC's XRG and Qatar-linked UCC hold two thirds of the equity](https://www.lacaribenanews.com/trinidad-venezuela-cross-border-gas-loran-manatee-2026/).

So the two dates sit two quarters apart, and the later one depends on the earlier. A Couva supplier quoting for work inside that plant is quoting against a gas schedule, not a construction schedule.

For the near term the useful figure is the smaller one. Refurbishment is running now, and 350 of those jobs belong to that phase.

## How does the scrap export ban sit beside it?

Awkwardly, and nobody has joined them up.

Scrap iron is feedstock for a steel mill. Trinidad is closing its scrap export trade, and [the Prime Minister says the industry ends on 31 December while the order in force extends dealers to October 2027](https://www.lacaribenanews.com/trinidad-scrap-iron-copper-export-ban-legal-notice-831-2026/). A mill at Point Lisas is being refurbished in the same window.

Neither announcement mentions the other. Whether scrap kept in the country by the export ban is meant to feed the restarted plant is not stated in either one. For a scrap dealer losing an export market, that is the question worth asking, and it has no published answer.

## How many development nodes are there?

The sources disagree, and the disagreement is a year old.

| Source                                      | Date             | Nodes      | Projects   | Value stated                |
| ------------------------------------------- | ---------------- | ---------- | ---------- | --------------------------- |
| Trinidad Express, at the launch             | 7 Nov 2025       | **12**     | 129        | none, "multibillion-dollar" |
| Trinidad Guardian, via Minister John        | Feb 2026         | **13**     | 129        | none                        |
| Trinidad Guardian, via Minister John        | 22 Nov 2026      | **13**     | 129        | **$112 billion**            |
| ttglobalhub.gov.tt, the Government's portal | read 24 Nov 2026 | not stated | not stated | not stated                  |
| Invaders Bay, the one project under way     | 20 Nov 2026      | n/a        | 1          | TT$1.75 billion, private    |

*The Government's own site states none of the three headline figures a supplier would use. Source: La Caribeña News reading of ttglobalhub.gov.tt, 24 November 2026.*

A node is how the programme groups projects by place, so the count sets how many separate procurement conversations a region faces. Twelve and thirteen are both on the record from the same programme, a year apart. The portal settles nothing, because it does not use the word.

## What does this mean for a firm in Couva?

Three things, and only one of them is a number.

The figure she gave cannot be checked against anything the Government publishes. The work she pointed at is partly real and already running, in the form of a steel plant refurbishment with a stated job count and a 2027 production target. And the route in is a log-in page on a tender system, not the glossy portal that carries the Prime Minister's photograph.

Preparation, in that setting, means registering on UDeCOTT's eTender system before January rather than waiting for an announcement. The minister is right that firms can miss this. The portal is part of how.

One more thing is moving while the programme waits. The Blueprint is branded a global logistical hub, and [Berbice now has a working port with a signed customer and two more coming, after Guyana used Trinidad and Jamaica for transshipment for decades](https://www.lacaribenanews.com/berbice-three-ports-cgx-customer-trinidad-jamaica-transshipment-2026/). Trinidad is planning the hub on a ten-year clock. Its largest neighbour is building the reason not to need one.

### What the title card shows

\- The Revitalisation Blueprint is worth $112 billion across 13 development nodes and 129 projects over ten years. Source: Minister of Works and Infrastructure Jearlean John, Couva Point Lisas Chamber of Commerce, 22 November 2026, reported by the Trinidad Guardian. - "Do not miss future business opportunities because you failed to prepare." Source: Jearlean John, same remarks. - The programme's portal at ttglobalhub.gov.tt names ten projects and states no value in its visible text. Source: La Caribeña News reading of the site, 24 November 2026\. - The portal's Send Brief and Go to Shop links both return a 404, and it lists info@website.com as a contact. Source: La Caribeña News reading of the site, 24 November 2026\. - Expression Of Interest on the portal opens UDeCOTT's eTender log-in at udecott.etenderworld.tt. Source: La Caribeña News reading of the site, 24 November 2026\. - Tenders for the Chaguanas overpass works were expected around January, works late January to February, subject to procurement. Source: Jearlean John, 22 November 2026\. - The Point Lisas steel plant restarts on a US$250 million investment by Pinnacle Steel and Vanadium, with 350 refurbishment jobs and 500 permanent, targeting first production by the end of 2027\. Source: Trinidad Express, 11 August 2026\. - Ibis Steel is a subsidiary of Pinnacle Steel and Vanadium, refurbishment began on 10 August 2026, the plant uses gas-based direct reduction, and no gas supply agreement had been announced. Source: La Caribeña News, 15 August 2026\. - Additional natural gas is expected to reach the national grid from the second quarter of 2027\. Source: Jearlean John, 22 November 2026\. - The Trinidad Express described 129 projects under 12 development nodes at the launch on 6 November 2025\. Source: Trinidad Express, 7 November 2025.

### The entities

\- **Revitalisation Blueprint:** the Government of Trinidad and Tobago's 129-project programme, branded the Trinidad and Tobago Global Logistical Hub, launched in November 2025\. - **Jearlean John:** Minister of Works and Infrastructure, and the programme's lead minister. - **Couva Point Lisas Chamber of Commerce:** the chamber for the country's largest industrial estate, whose president is Deoraj Mahase. - **Urban Development Corporation of Trinidad and Tobago (UDeCOTT):** the state development corporation, which runs the eTender system the portal points to. - **Point Lisas Industrial Port Development Corporation (Plipdeco):** the state-owned company that runs the Point Lisas estate and port. - **Pinnacle Steel and Vanadium:** the United States metals investor restarting the Point Lisas steel plant, whose chief executive is Edwin Bennett. - **Ibis Steel Company of Trinidad and Tobago Limited:** the local subsidiary of Pinnacle Steel and Vanadium, and the company the minister named in the Plipdeco negotiations over the same plant.

## Frequently asked questions

How much is Trinidad's Revitalisation Blueprint worth?

The Minister of Works and Infrastructure, Jearlean John, put it at $112 billion across 129 projects and 13 development nodes over ten years, speaking to the Couva Point Lisas Chamber of Commerce on 22 November 2026\. That is about US$16.5 billion. The figure rests on her statement. It does not appear on the programme's own portal at ttglobalhub.gov.tt, and the independent coverage of the 2025 launch did not carry a total.

How does a contractor bid for Revitalisation Blueprint work?

Through UDeCOTT's eTender system. The Expression Of Interest link on the programme's portal opens a log-in page at udecott.etenderworld.tt, and a firm that has not used it before has to create an account. The portal does not explain this in words, and its other two action buttons return a 404.

When are the next Blueprint tenders in Trinidad?

Around January 2027 for the Chaguanas congestion works, on the minister's account of 22 November 2026, with construction possibly starting between late January and February, subject to procurement. Those works include overpasses at Monroe Road, Price Plaza, Brentwood, Mulchan Seuchan Road and Chase Village.

Is the Point Lisas steel plant reopening?

Refurbishment began in August 2026\. The Trinidad Express reported a US$250 million investment by Pinnacle Steel and Vanadium, 350 jobs during refurbishment and 500 permanent positions, and a target of first production by the end of 2027\. The plant also intends to produce vanadium. The local vehicle is Ibis Steel Company of Trinidad and Tobago Limited, a subsidiary of Pinnacle, and the minister named it in negotiations with Plipdeco over the same site. The plant uses gas-based direct reduction, and no gas supply agreement had been announced when refurbishment began.

How many of the 129 projects have broken ground?

One on the public record. The sod was turned at Invaders Bay on 20 November 2026, on a TT$1.75 billion privately financed development.