# Suriname Took a US$1.6 Billion Decision on Offshore Gas. First Gas Is Mid-2030, and Its 2027 Budget Is Short SRD 10.8 Billion.
- URL: https://www.lacaribenanews.com/suriname-krakawi-fid-1-6-billion-first-gas-2030-block-52-2026/
- Published: 2026-11-27T16:50:17.000Z
- Updated: 2026-11-27T16:50:18.000Z
- Description: PETRONAS and Staatsolie took a final investment decision on 26 November 2026 to develop the Sloanea gas field in Block 52 offshore Suriname. The project, KrakaWi, costs US$1.6 billion and first gas is expected in mid-2030.
- Author: Theon Alleyne
- Tags: Energy, Suriname, Business, Beat: extractives-sovereign-wealth, MSME: indirect

**Quick summary:** PETRONAS and Staatsolie took a final investment decision on 26 November to develop the Sloanea gas field in Block 52 offshore Suriname. The project is called KrakaWi. It costs US$1.6 billion. First gas is expected in mid-2030, and the field is to run for 25 years.

By LCN Business Desk

Suriname now has two dated offshore projects. On Thursday PETRONAS and Staatsolie decided to build the second, a US$1.6 billion gas development in Block 52.

The gas arrives in mid-2030.

## What exactly was decided?

A field development, and a name. The partners are PETRONAS, acting through PETRONAS Suriname E&P B.V., and the state oil company Staatsolie. They took the final decision to develop the Sloanea gas field, in Block 52 offshore Suriname, [Staatsolie said](https://www.staatsolie.com/en/news/petronas-and-staatsolie-take-final-investment-decision-on-suriname-s-first-offshore-gas-development/?ref=lacaribenanews.com).

PETRONAS leads with an 80 per cent participating interest. Staatsolie holds 20 per cent and will invest in proportion to it.

The project is called KrakaWi. The name is Sranan Tongo for "supports us", from kraka, supports, and wi, we. Staatsolie approved the field development plan two days before the decision, on 24 November.

Two company heads took it to President Jennifer Geerlings-Simons. They are Tan Sri Tengku Muhammad Taufik, who leads PETRONAS, and Annand Jagesar, Managing Director of Staatsolie. Gregory Rusland, Minister of Natural Resources, was also there.

"This is a wonderful project for Suriname," Jagesar said.

Geerlings-Simons put the obligation wider. "This project is not just about PETRONAS and Staatsolie," she said. "It affects our entire country, and that is why it is our shared responsibility."

## How long did this take?

Thirteen years from the contract, and six from the gas. Staatsolie and PETRONAS signed the production sharing contract for Block 52 in 2013.

| Step                                      | When             |
| ----------------------------------------- | ---------------- |
| Production sharing contract for Block 52  | 2013             |
| Sloanea-1 gas discovery                   | late 2020        |
| Sloanea-2 appraisal well and well testing | 2024             |
| Commercial Field approved for Sloanea-1   | 11 November 2025 |
| Field development plan approved           | 24 November 2026 |
| Final investment decision                 | 26 November 2026 |
| First gas expected                        | mid-2030         |

*As set out by Staatsolie on 26 November 2026.*

Four more years follow the decision before any gas is sold.

## What does the field hold, and what will it make?

Gas, chilled at sea and shipped out.

| Measure          | Figure                          |
| ---------------- | ------------------------------- |
| Investment       | US$1.6 billion                  |
| Recoverable gas  | 97 billion cubic metres         |
| LNG capacity     | about 1.5 million tonnes a year |
| Project life     | 25 years                        |
| Production wells | 4                               |

*As stated by Staatsolie on 26 November 2026.*

Four offshore wells feed it, through subsea infrastructure, to a floating plant that does the chilling.

Staatsolie puts a second use on it. The project lays a foundation for producing oil from reservoirs that carry a lot of gas, and makes further offshore gas developments more attractive.

## When does the money actually arrive?

Not in this budget, and not in the next three. First gas is mid-2030.

Suriname's nearer milestone is oil. [First oil from GranMorgu is due in the first half of 2028](https://www.lacaribenanews.com/suriname-petroleum-law-local-content-granmorgu-first-oil-2026/).

The gap, meanwhile, is in the present tense. [Suriname's draft 2027 budget, presented on 30 September, sets revenue at SRD 70.1 billion against spending of SRD 80.9 billion](https://www.lacaribenanews.com/suriname-2027-budget-deficit-srd-108bn-simons-jaarrede-arrears-2026/). That is a deficit of SRD 10.8 billion, or 4 per cent of gross domestic product.

A 25-year project that starts producing in 2030 does not close a 2027 deficit.

## How does that compare with Trinidad's deepwater gas?

Trinidad has the acreage and not the decision. [Woodside Energy agreed on 6 August to sell its 70 per cent operated interest in the Calypso deepwater gas project to bp](https://www.lacaribenanews.com/bp-woodside-calypso-trinidad-gas-project-exit-2026/). It sold eight days after flagging impairments of US$160 million to US$200 million. No investment decision, capital cost or first-gas date is published for Calypso.

Suriname now has all three. A cost of US$1.6 billion, a date of mid-2030 and a decision taken.

## What should a Caribbean reader take from this?

That Suriname's offshore calendar now has two fixed dates and its fiscal problem has none.

A supplier in Paramaribo can plan against first oil in the first half of 2028 and first gas in mid-2030\. Staatsolie says the project creates opportunities for local employment and entrepreneurship, and gave no employment figure.

The rule meant to direct that work to Surinamese firms is thin. Suriname has required contractors to prefer Surinamese labour and supply since the Petroleum Law 1990\. No percentage, no category and no penalty is attached to it. [Suriname's oil minister has warned that concentrating local content on oil and gas would drain the rest of the economy](https://www.lacaribenanews.com/suriname-summit-duurzaam-3-0-oil-diversification-local-content-2026/).

Staatsolie has said what the state will receive and not how much. The revenues will consist of royalties, the State's share of production revenues and taxes, beginning when production starts in mid-2030\. No royalty rate, no share and no tax rate is published.

### Title card, text equivalent

All figures on the title card, with their sources.

The panel sets out the KrakaWi development: an investment of US$1.6 billion, 97 billion cubic metres of recoverable gas, a liquefied natural gas capacity of about 1.5 million tonnes a year, a project life of 25 years, and four offshore production wells. Source: Staatsolie's statement of 26 November 2026.

The four figures in the bottom strip:

- Mid-2030: when first gas is expected. Source: the same.
- First half of 2028: when first oil from GranMorgu is due. Source: La Caribeña News on Suriname's petroleum law and local content.
- SRD 10.8 billion: the deficit in the draft 2027 budget, equal to 4 per cent of gross domestic product. Source: La Caribeña News on the budget presented on 30 September 2026.
- 24 November: when Staatsolie approved the field development plan, two days before the investment decision. Source: Staatsolie, 26 November 2026.

### Entities named in this report

- **Staatsolie** is Suriname's state oil company and a partner in the project.
- **PETRONAS** is Malaysia's state energy company, acting through **PETRONAS Suriname E&P B.V.**
- **The Sloanea gas field** sits in **Block 52** offshore Suriname.
- **KrakaWi** is the name given to the development.
- **Annand Jagesar** is Managing Director of Staatsolie.
- **Tan Sri Tengku Muhammad Taufik** is President and Group Chief Executive Officer of PETRONAS.
- **Jennifer Geerlings-Simons** is President of Suriname.
- **Gregory Rusland** is Suriname's Minister of Natural Resources.
- **Sranan Tongo** is Suriname's lingua franca, and gives the project its name.
- **GranMorgu** is the separate offshore oil development due to produce first oil in the first half of 2028.

## Frequently asked questions

What did PETRONAS and Staatsolie decide?

They took a final investment decision on 26 November 2026 to develop the Sloanea gas field in Block 52 offshore Suriname. The project is named KrakaWi and will cost US$1.6 billion.

How much gas is there and what will it produce?

The field is estimated to hold 97 billion cubic metres of recoverable gas. A floating liquefied natural gas facility will have a capacity of about 1.5 million tonnes a year, over a project life of 25 years, fed by four offshore production wells.

When does production start?

First gas is expected in mid-2030\. Suriname's nearer offshore milestone is first oil from GranMorgu, due in the first half of 2028.

Will it help the 2027 budget?

No. The draft 2027 budget carries a deficit of SRD 10.8 billion, about 4 per cent of gross domestic product, and the gas does not flow until mid-2030.

What does it mean for Surinamese firms?

Staatsolie says the project creates opportunities for local employment and entrepreneurship, without giving a figure. Suriname's preference rule for Surinamese labour and supply dates from the Petroleum Law 1990 and carries no percentage, category or penalty.