# Longtail's Topsides Will Be Built in Tianjin for US$240 to US$315 Million. The Contract Took Effect on 24 September and Named No Country.
- URL: https://www.lacaribenanews.com/longtail-topsides-bomesc-tianjin-240-315-million-no-country-named-2026/
- Published: 2026-11-27T01:42:13.000Z
- Updated: 2026-11-27T01:42:15.000Z
- Description: Bomesc Offshore Engineering told the Shanghai market on 29 September that a Tianjin subsidiary had signed with an SBM Offshore unit for an FPSO's topsides modules. The contract took effect on 24 September and named no project. Guyana's Longtail was tied to it two months later.
- Author: Theon Alleyne
- Tags: wire, celac wire, Beat: extractives-sovereign-wealth, MSME: indirect

**Quick summary:** Bomesc Offshore Engineering told the Shanghai market on 29 September that it had signed an FPSO topsides contract with an SBM Offshore unit. The price is CNY 1.6bn to 2.1bn, which is US$240m to US$315m. It took effect on 24 September. The filing named no project. Guyana's Longtail was tied to it two months later.

By LCN Business Desk

A Chinese yard has the contract to build the topsides for Guyana's eighth oil development. It took the work on 24 September.

Nobody in Guyana could have known. The filing that disclosed it named no project and no country.

## Who is building Longtail's topsides?

Tianjin Bomesc. The yard belongs to Bomesc Offshore Engineering, listed in Shanghai under the code 603727, and the counterparty is Single Buoy Moorings Inc., a wholly owned unit of SBM Offshore.

The scope is the design, the materials and the building of the topsides modules. The process decks sit on the vessel's hull and do the work of separating oil, water and gas.

The modules are to be built at the company's Lingang yard in Tianjin. SBM pays against measured progress and the milestones in the contract.

Completion is planned for the second half of 2028.

## How much is the contract worth?

Between CNY 1.6 billion and CNY 2.1 billion. The spread is not uncertainty about the deal. It is written into the price.

|                             | Yuan          | US dollars      |
| --------------------------- | ------------- | --------------- |
| Floor                       | 1,600 million | **240 million** |
| Ceiling                     | 2,100 million | **315 million** |
| Bomesc's whole 2025 revenue | 1,900 million | 285 million     |

*Converted at the European Central Bank's reference rates of 26 November 2026, which give 6.6602 yuan to the US dollar.*

The filing sets the price as a fixed part plus a variable part, and the variable part is calculated on the work volume as currently estimated. The final figure is settled when the work is done.

**One contract is worth about what the whole company earned last year.** Bomesc reported revenue of CNY 1.9 billion for 2025, and its own market valued it at CNY 5.3 billion on the day it disclosed this.

## Why does the figure in the headlines say US$315 million?

Because that is the ceiling. [Kaieteur News reported the contract on Thursday](https://kaieteurnewsonline.com/2026/11/26/chinese-firm-secures-us315m-contract-for-longtail-fpso-works/?ref=lacaribenanews.com) at US$315 million, which is the top of the band at this week's rate.

The arithmetic is right. What it describes is the most the contract can pay, not what it will pay.

Upstream put the same yuan range at US$239 million to US$313 million, on a rate a little different from today's. A reader comparing the two numbers is looking at one contract and two exchange rates.

## What did the filing not say?

Guyana. It named no project, no field and no operator.

Bomesc later confirmed that one of its undisclosed SBM topsides contracts is the Longtail vessel, and Upstream reported that confirmation on 24 November. Kaieteur tied it to the contract that took effect on 24 September.

So the sequence ran in this order. The work was awarded in September, disclosed in Shanghai in September without a destination, and placed in Guyana in late November.

It has happened once before on this project. TechnipFMC's two Longtail subsea contracts, which [this newspaper put at between US$575 million and US$1.25 billion](https://www.lacaribenanews.com/technipfmc-longtail-subsea-local-content-reserves-none-2026/), were in its order book before the investment decision was public.

## Is this the only SBM contract Bomesc signed?

No. There are two, five weeks apart, and they are not the same contract.

|                       | Effective         | Yuan           | US dollars   | Completion          |
| --------------------- | ----------------- | -------------- | ------------ | ------------------- |
| The Longtail contract | 24 September 2026 | 1.6bn to 2.1bn | 240m to 315m | second half of 2028 |
| A second contract     | 25 October 2026   | 2.4bn to 3.0bn | 360m to 450m | April 2029          |

*The second was disclosed as announcement 2026-045\. Nothing this newspaper has read ties it to a Guyanese project.*

**Together the two could pay up to about US$765 million, which is more than two and a half times what Bomesc earned in 2025.** Reports giving a single figure near US$420 million are describing the October contract, not this one.

## Can any of this work be Guyanese?

None of the building. The modules are made in Tianjin, so the fabrication hours are spent 14,000 kilometres from the field they will serve.

Nor does the law reach it. Guyana's Local Content Act lists forty categories and reserves a minimum Guyanese share in each. [No category covers offshore vessels or subsea services](https://www.lacaribenanews.com/exxonmobil-longtail-fid-12-5-billion-pipeline-not-committed-2026/), and topsides fabrication sits outside the list in the same way.

One part of Longtail does carry a reserved share. [SBM Offshore expects to operate the vessel for an initial ten years, and crewing is reserved at 50 per cent](https://www.lacaribenanews.com/sbm-offshore-longtail-fpso-contract-ten-year-operate-crewing-fifty-per-cent-2026/). The share attaches to running the vessel, not to building it.

## What should a Caribbean reader take from this?

That a Caribbean supplier can take the news of a contract last. The disclosure arrives first in another country's market, in another language, and on that market's timetable.

ExxonMobil committed US$12.5 billion to Longtail on 12 November. Two of the packages inside that figure have now been named by the contractors who won them, in Houston and in Shanghai, rather than in Georgetown. [Guyana licensed the project as its first non-associated gas development, and the fiscal terms are not on the public record](https://www.lacaribenanews.com/guyana-longtail-production-licence-profit-share-exxon-venezuela-2026/).

A Guyanese firm reading only the local record would have learned of the topsides award on Thursday. A Shanghai investor could read it on 29 September, in a filing that happened not to mention where the vessel was going.

The next date on the file is the second half of 2028, when the modules are due out of Tianjin.

### Title card, text equivalent

All figures on the title card, with their sources.

- US$240 million to US$315 million: the contract band, converted from CNY 1.6 billion to 2.1 billion. Sources: Bomesc Offshore Engineering's disclosure of 29 September 2026 as reported by China Securities Journal and Chanlnews, and the European Central Bank's reference rates of 26 November 2026.
- 24 September 2026: the date the contract took effect. Source: the same disclosure.
- CNY 1.9 billion: Bomesc's revenue for 2025, about US$285 million. Source: the same reporting, citing the company's 2025 annual report.
- 2.4 billion to 3.0 billion yuan: a second SBM topsides contract, effective 25 October 2026\. Source: announcement 2026-045, as reported.
- Second half of 2028: planned completion of the Longtail topsides. Source: the 29 September disclosure.
- 603727: Bomesc's Shanghai listing code. Source: the same.

### Entities named in this report

- **Bomesc Offshore Engineering** is the Shanghai-listed builder, code **603727**, and **Tianjin Bomesc** is the wholly owned subsidiary that signed.
- **Single Buoy Moorings Inc.** is the **SBM Offshore** unit that awarded the contract.
- **Longtail** is Guyana's eighth offshore development, sanctioned by **ExxonMobil** at US$12.5 billion.
- **TechnipFMC** holds the Longtail subsea contracts.
- **Guyana's Local Content Act** lists forty categories and covers neither offshore vessels nor subsea services.
- **Kaieteur News** and **Upstream** reported the Guyana link.
- **The European Central Bank** publishes the reference rates used for the conversion here.

## Frequently asked questions

Who is building the topsides for Guyana's Longtail vessel?

Tianjin Bomesc, a subsidiary of Bomesc Offshore Engineering of Shanghai. It signed with Single Buoy Moorings Inc., a unit of SBM Offshore, and the work is to be done at its Lingang yard in Tianjin.

What is the contract worth?

Between CNY 1.6 billion and CNY 2.1 billion, which is US$240 million to US$315 million at the European Central Bank's rates of 26 November 2026\. The price has a fixed part and a part that varies with the work volume, so the final figure is set on completion.

Why do reports give different dollar figures?

They convert the same yuan range at different rates, and some quote only the ceiling. One report also gives a figure near US$420 million, which belongs to a second Bomesc contract with SBM rather than to this one.

When did the contract take effect?

On 24 September 2026\. Bomesc disclosed it to the Shanghai market on 29 September, in a filing that named no project or country. The Longtail link was reported on 24 November.

Does Guyana's Local Content Act reserve any of this work?

No. Its forty categories cover neither offshore vessels nor subsea services, and topsides fabrication falls outside them too. The modules are also built in China, so the work is beyond the Act's reach in practice as well as on paper.

What part of Longtail does carry a Guyanese share?

Crewing the vessel, reserved at 50 per cent. SBM Offshore expects to operate Longtail for an initial ten years.