# Guyana's Biggest Road Contract at the Time Was Signed for Three Years in May 2022. It Is 89 Per Cent Done, and the Minister Has Named 8 December.
- URL: https://www.lacaribenanews.com/linden-mabura-road-8-december-liquidated-damages-alya-construtora-cade-2026/
- Published: 2026-11-25T19:24:41.000Z
- Updated: 2026-11-25T19:24:44.000Z
- Description: Public Works Minister Rt. Hon. Bishop Juan Edghill told the National Assembly on 23 November 2026 that the Linden to Mabura Hill road is 89 per cent complete and due on 8 December, with liquidated damages if it slips. The contract was signed on 20 May 2022 for three years.
- Author: Theon Alleyne
- Tags: Guyana, Roads, Procurement, Infrastructure, Analysis, Beat: procurement-project-finance, MSME: indirect

**Quick summary:** Public Works Minister Rt. Hon. Bishop Juan Edghill told the National Assembly on 23 November 2026 that the Linden to Mabura Hill road is 89 per cent complete and due on 8 December, with liquidated damages if it slips. The contract was signed on 20 May 2022 for a stated term of three years.

By LCN Business Desk

A three-year contract signed in May 2022 should have ended in May 2025.

This one is still running. Parliament approved more money for it on Monday, and the minister responsible named a new date and a penalty in the same answer.

## What did the minister tell the National Assembly?

That the road is 89 per cent done, that 8 December is the date, and that the contract has clauses he is prepared to use.

Rt. Hon. Bishop Juan Edghill, the Minister of Public Works, was answering questions on his ministry's G$27.4 billion in supplementary funding. He said December 8 was a revised completion date, [set after the contractor asked for more time](https://kaieteurnewsonline.com/2026/11/25/linden-mabura-road-89-complete-set-for-december-8-handover-edghill/?ref=lacaribenanews.com). "Based on the extension of time that was requested by the contractor, the date is the 8th of December," he told the committee.

Then the warning. "If they go past the 8th, clauses of the contract will be invoked, which will include liquidated damages."

He did not say what those damages come to. The contract is not a public document. The Caribbean Development Bank published an award notice for it, giving every bid price, the winner and the duration, and stopped there. So the rate sits in a document the people paying for the road have never seen.

## How many completion dates has this contract had?

Six, counting only the dates ministers and the project's financiers put on the record.

| When             | What was said                                      | Reported progress                                   |
| ---------------- | -------------------------------------------------- | --------------------------------------------------- |
| 20 May 2022      | Contract signed, three-year duration               | works begin                                         |
| December 2023    | Minister says the pace is not acceptable           | 25 per cent                                         |
| January 2025     | Deadline reset to 29 October 2025                  | 33 per cent                                         |
| April 2025       | "Stern warning" to the contractor                  | 40 per cent, with 80 per cent of contract time gone |
| January 2026     | Britain confirms December 2025 is not achievable   | 62 per cent                                         |
| February 2026    | Government information service reports a milestone | 86 per cent                                         |
| 23 August 2026   | A revised date passes                              | reported above 80 per cent                          |
| 23 November 2026 | 8 December named, with liquidated damages          | 89 per cent                                         |

The percentages in that last column do not travel at a steady speed. They move twenty-four points between January and February 2026, then three points across the nine months to November. No source reconciles the two rates.

The lost year is documented. [The contractor halted procurement and construction on 18 June 2024 and resumed on 12 August 2024](https://inewsguyana.com/linden-mabura-road-upgrade-contractor-resumes-work-after-losing-72-of-construction-time/?ref=lacaribenanews.com). Officials put the downtime that followed at about three quarters of available construction time.

## Who is building the road?

Álya Construtora, which is the company that used to be called Construtora Queiroz Galvão.

The main civil works contract was signed on 20 May 2022, with a stated duration of three years. Its value is the US$190 million figure the government quotes, recorded as G$32.501 billion. Those particulars come from the Bank's own records, [set out by Village Voice in August](https://villagevoicenews.com/2026/08/09/linden-mabura-highway-three-year-contract-runs-into-a-fifth-year-as-billions-keep-flowing/?ref=lacaribenanews.com), when the contract was already past its term. It was described at the signing as the largest project the Bank had ever funded. Guyana has signed bigger road work since: the eight Craig to Land of Canaan contracts come to G$52.56 billion between them. Village Voice set that out from the Caribbean Development Bank's own records in August, when the contract was already past its term.

The name changed before the ink was dry. Queiroz Galvão said in April 2022 that its building arm would trade as Álya. The Guyana contract was signed a month later. Guyanese reports used the old name at the signing and the new one later, and [by January 2026 the project stood at 62 per cent](https://www.stabroeknews.com/2026/01/14/news/guyana/linden-to-mabura-hill-road-upgrade-at-62/?ref=lacaribenanews.com).

Anyone tracking this contract through the public record has to follow a company across two names.

## Who else bid for it?

Four other firms bid, and all of them were foreign.

The call for prequalification went out in February 2021\. Ten contractors were prequalified and the Bank approved that list in October 2021\. Bidding ran from October 2021 and closed in December 2021\. Five firms bid: three from China and two from Brazil. The Bank records four bids rejected and the method as open international competitive bidding.

On the Bank's own record, no Guyanese firm bid. Guyanese reporting in December 2021 described one bidder as a Guyanese company; the Bank gives that bidder's country as Brazil.

## What happened in Brazil last week?

Brazil's competition authority settled a cartel case in which that company is a party.

On 18 November the tribunal of the Conselho Administrativo de Defesa Econômica, known as CADE, ruled on a cartel in the bidding for five stadiums built for the 2014 World Cup. It fined Construtora OAS, Delta Construções and three individuals about R$135 million. The cartel ran from 2007 to the middle of 2011.

The case is Processo Administrativo nº 08700.006630/2016-88.

**Three official records identify that company, and they agree.**

Brazil's own competition authority names the settling party as "Construtora Queiroz Galvão (atualmente Álya Construtora S.A.)" in its ruling. A São Paulo city comptroller decision published in October 2024 says the same thing in registry terms: Álya Construtora S/A is the current name of Construtora Queiroz Galvão S.A., under one tax number, CNPJ 33.412.792/0001-60\. The Caribbean Development Bank's award notice names Guyana's winning bidder as Construtora Queiroz Galvão S.A., of Brazil.

So the regulator, the registry and the lender describe one company. Guyanese reporting has used both names at different dates, which is what a name change looks like from outside.

One gap remains in that chain. The Bank's award notice carries no tax number. So the match between the firm it names and the firm on the Brazilian register rests on an exact company name and a country, not on a registration number.

The company now building the Linden road sits on the other side of that case. Three firms settled instead, together with eleven individuals. [They were Odebrecht, Carioca Christiani Nielsen and Construtora Queiroz Galvão, now Álya Construtora](https://valor.globo.com/empresas/noticia/2026/11/18/cade-condena-oas-e-delta-por-cartel-em-licitacoes-de-estadios-da-copa-do-mundo-de-2014.ghtml?ref=lacaribenanews.com). Each admitted the practice under investigation. Together they agreed to pay about R$120 million to a Brazilian public fund, which is roughly US$22 million at early-November rates. For those who settled, the case is on hold until they are shown to have complied.

The bid list runs alongside that. Queiroz Galvão won the Guyana contract. Odebrecht owns OECI, which led the joint venture that bid against it. Both groups settled the same cartel case.

The settlement has not been reported in the Guyanese press.

The case concerns Brazilian bidding, and nothing else. It makes no allegation about the Guyana contract, and neither has the minister. La Caribeña News set out the case in full on 25 November, including what each instrument means: [it fined two builders and three individuals, while three other firms had already settled](https://www.lacaribenanews.com/brazil-world-cup-stadium-cartel-cade-fines-settlements-caribbean-builders-2026/).

The link is narrower and it is twofold. The firm holding this contract admitted bid-rigging to its home regulator seven days before a Guyanese minister warned it about a deadline. And the field it won from contained one other group that admitted the same thing.

## What does the published record show about the work itself?

It names no subcontractor, and it carries one dispute that has never been closed.

The published record names no subcontractor on this road. Not the ministry's project briefs, not the Bank's procurement notices, not the register of awarded tenders. What is published is headcount. The contractor has described about 900 workers and more than 300 pieces of heavy equipment.

The register is a known weak point. This newspaper reported that [the eight contracts for the Craig to Land of Canaan highway do not appear on it at all](https://www.lacaribenanews.com/guyana-awarded-tenders-register-missing-road-award-record-quality-2026/). The same register carries 2,153 rows with no currency and 1,456 with no date of award.

Then there is Malali, an Arawak community of just over 230 people about 50 miles from Linden. In November 2023 the Guyana Geology and Mines Commission ordered the contractor to stop mining laterite on its land. The firm had no licence for it. The village Toshao, Orlayne Williams, said the council had approved the mining before the Commission acted. Residents said they were not fully paid for what was taken.

Ganesh Mahipaul, an opposition Member of Parliament, put it to the Public Accounts Committee. He asked for two things to be sent there: the contract with the Brazilian firm, and the signed compensation agreements. Vladim Persaud, the Permanent Secretary of the Ministry of Public Works, confirmed the cease order and said the ministry was reviewing it. Three years on, the committee's record carries no outcome: not the contract, not the compensation agreements, and not a lifting of the order.

## What is the new money for?

The money buys another 30 kilometres at a price set five years ago.

The Ministry of Public Works was approved G$27.4 billion. Of that, G$4,769,340,207, or about G$4.77 billion, was sought to speed up work on this road and the Kurupukari Bridge. Edghill called it "$4.9B" when he explained it to the committee, which is the figure that went into the record of the exchange rather than the one on the paper. Edghill said it would take the road about 30 kilometres past Mabura Hill. The government had engaged the contractor at the same 2021 rate, he said.

That allocation sits inside the [G$89.8 billion of extra spending the National Assembly approved in one sitting](https://www.lacaribenanews.com/guyana-supplementary-89-8-billion-cash-grant-portal-closes-30-november-2026/), on 23 November.

The first phase is paid for three ways. A US$112 million loan from the Caribbean Development Bank, a £50 million British grant, and US$12 million from Guyana. The British money comes through the UK Caribbean Infrastructure Fund, [a separate facility from UK Export Finance](https://www.lacaribenanews.com/uk-business-mission-guyana-trade-surplus-27-million-ukef-ceiling-2026/).

## What should a Guyanese business take from this?

That a date in a government road announcement is a forecast, and the contract is where the obligations sit.

A supplier pricing work off a published completion date has watched six of them pass or move on this one project. A subcontractor weighing the Kurupukari extension is being offered 2021 rates in 2026\. That is the government's own stated position, and nobody has complained about it publicly.

Malali is still open. There is a cease work order, a village that says it was not fully paid, and a request for two documents that has produced neither. That is a gap in the record rather than a finding about anybody. The contract exists. Whether signed compensation agreements do is part of what the committee asked.

### The entities

\- **Álya Construtora:** the Brazilian contractor on the Linden to Mabura Hill road, formerly Construtora Queiroz Galvão S.A. - **Rt. Hon. Bishop Juan Edghill:** Guyana's Minister of Public Works. - **Caribbean Development Bank:** lender of US$112 million to the project, its largest single project to date at the time of signing. - **UK Caribbean Infrastructure Fund:** the British facility providing the £50 million grant, separate from UK Export Finance. - **Conselho Administrativo de Defesa Econômica (CADE):** Brazil's competition authority, which ruled on the 2014 World Cup stadium cartel on 18 November 2026\. - **Public Accounts Committee:** the committee of Guyana's National Assembly that examined the laterite dispute in November 2023\. - **Malali:** an Arawak community of just over 230 people about 50 miles from Linden. - **Ganesh Mahipaul:** the opposition Member of Parliament who asked for the contract and compensation agreements. - **Guyana Geology and Mines Commission:** the body that issued the cease work order. - **OECI S.A.:** Odebrecht Engenharia e Construção Internacional, the Brazilian group's international building arm, which led a losing joint venture bid.

### What the title card shows

20 May 2022: the date the main civil works contract was signed, for a stated term of three years. May 2025: when that term would have ended. Six: completion dates named or reset on the public record since. 89 per cent: reported complete by the Minister of Public Works, Rt. Hon. Bishop Juan Edghill, on 23 November 2026\. 8 December 2026: the revised completion date, set after the contractor requested an extension, with liquidated damages if it slips. 0: subcontractors named in the published record for this project. G$4,769,340,207: the supplementary sum sought to speed up this road and the Kurupukari Bridge, which the minister called $4.9B in the chamber.

## Frequently asked questions

When is the Linden to Mabura Hill road due to be finished?

8 December 2026, on the date the Minister of Public Works gave the National Assembly on 23 November. He said it was a revised date set after the contractor requested an extension, and that the road was 89 per cent complete.

What happens if the contractor misses 8 December?

The minister said clauses of the contract will be invoked, including liquidated damages. He did not state the rate or the amount, and the contract is not published, so the size of any penalty cannot be checked from the public record.

Who is the contractor?

Álya Construtora, a Brazilian firm that was called Construtora Queiroz Galvão S.A. when the contract was signed on 20 May 2022\. The construction arm was renamed Álya in April 2022, a month before the signing, which is why Guyanese records carry both names.

Is the Brazilian cartel case about the Guyana road?

No. It concerns bidding for five stadiums built or renovated in Brazil for the 2014 World Cup, in a cartel the authority dates from 2007 to mid-2011\. Álya Construtora signed a cessation agreement acknowledging the practice and committing to payment. It makes no allegation about the Guyana contract.

Did any Guyanese company bid for the contract?

No. Ten contractors were prequalified and five bid. Three were Chinese and two were Brazilian: OECI S.A. in joint venture with Castilho Engenharia, and Construtora Queiroz Galvão, which won. The Ministry of Finance named all five when it announced the award in February 2022.

What was the dispute at Malali?

In November 2023 the Guyana Geology and Mines Commission ordered the contractor to stop mining laterite without a licence on land belonging to the Arawak community of Malali. The village Toshao said the council had approved it; residents said they were not fully paid. An opposition MP asked the Public Accounts Committee for the contract and the compensation agreements. No outcome has been published since.