# Guyana's Wales Gas Plant Reached US$956 Million. The Vice President Puts the Wires to Carry Its Power at US$4.8 Billion.
- URL: https://www.lacaribenanews.com/guyana-transmission-distribution-4-8-billion-jagdeo-wires-2026/
- Published: 2026-11-27T15:40:16.000Z
- Updated: 2026-11-27T15:46:17.000Z
- Description: Vice President Dr Bharrat Jagdeo told the manufacturers' awards dinner on 26 November that Guyana needs about US$2.3 billion for its transmission backbone and about US$2.5 billion for distribution, covering 1,500 kilometres and the transformers on it.
- Author: Theon Alleyne
- Tags: Energy, Guyana, Business, Beat: energy-transition-tariffs, MSME: indirect

**Quick summary:** Vice President Dr Bharrat Jagdeo spoke at the manufacturers' awards dinner on 26 November. Guyana needs about US$2.3 billion for its transmission backbone, he said, and about US$2.5 billion more for distribution. The work covers about 1,500 kilometres. He said the lines are overloaded and the system has no spare path.

By LCN Business Desk

Guyana has spent four years arguing about where its power will be generated. The Vice President has now put US$4.8 billion on the wires that carry it.

Vice President Dr Bharrat Jagdeo put the transmission backbone at about US$2.3 billion. He put distribution at about US$2.5 billion. He was [speaking on Thursday to the Guyana Manufacturing and Services Association's 31st awards dinner](https://inewsguyana.com/us5b-needed-to-modernise-guyanas-electricity-transmission-distribution-network-jagdeo/?ref=lacaribenanews.com).

## What does the network work cover?

About 1,500 kilometres, and the transformers on it. Jagdeo said the distribution programme involves replacing transformers and upgrading roughly that length of network.

It also covers new transmission backbones, stronger lines, substations and a modernised smart grid.

He gave two reasons for the work. Existing lines and transformers are overloaded as households and businesses add equipment. And the network has no redundancy, so damage to something as small as one pole can leave whole areas without power.

Jagdeo said GPL's customer count rose from 184,000 in 2019 to 231,000.

## How does that compare with the generation it carries?

The plant is a fraction of it. [Guyana approved G$24.7 billion more for the Wales gas plant on 23 November 2026, taking it to US$956 million](https://www.lacaribenanews.com/guyana-wales-gas-plant-cost-956-million-lindsayca-200-million-2026/).

|                       | US$             |
| --------------------- | --------------- |
| Transmission backbone | 2.3 billion     |
| Distribution network  | 2.5 billion     |
| **Wires, combined**   | **4.8 billion** |
| Wales gas plant       | 0.956 billion   |

*Plant cost as approved and reported by La Caribeña News on the Wales financing; network figures as stated by the Vice President on 26 November 2026.*

## What is the grid carrying now?

More than it was, and the published figures differ. Reports of the remarks agree on the 2019 base of 130 megawatts and on available capacity of 255 megawatts. On where peak demand stands now they range from 216 megawatts to above 260.

A fortnight earlier it was reported higher still. [Minister of Public Utilities Deodat Indar put peak demand close to 269MW against roughly 260MW of operating sets](https://www.lacaribenanews.com/guyana-peak-demand-269-megawatts-powership-venezuela-christmas-2026/), in this newspaper's report of 13 November.

No official has published the underlying series. A firm sizing a connection is choosing between readings some 50 megawatts apart.

## What does holding the tariff cost?

More than the tariff collects. Jagdeo said generating a kilowatt-hour costs US$0.3456 this year, on higher fuel, while the rate charged stayed at US$0.23.

| This year                                | G$             | About US$       |
| ---------------------------------------- | -------------- | --------------- |
| Electricity subsidy                      | 33 billion     | 158 million     |
| Capital subsidy for power infrastructure | 62 billion     | 297 million     |
| **Combined**                             | **95 billion** | **455 million** |

*Converted at about G$209 to the US dollar. Figures from [the Guyana Chronicle's report of the same remarks](https://guyanachronicle.com/2026/11/27/g95b-in-electricity-subsidies-this-year-cushion-households-businesses/?ref=lacaribenanews.com).*

"So just think about the scale of the financing and what we have to do, but we have no other choice to do it," he said.

The subsidy has a parliamentary trail. [G$8 billion of a G$12.9 billion public utilities request was fuel for GPL, and the government described it as buying a tariff that does not rise](https://www.lacaribenanews.com/guyana-financial-paper-3-eight-billion-gpl-fuel-tariff-2026/).

## When does the gas plant run?

The first half of 2027\. Jagdeo put completion of the single-cycle unit at the end of the first quarter of 2027, and the combined-cycle unit around June.

That timing matches what customers were told about their bills. [The Prime Minister tied the promised fall in bills to the plant running at full capacity, and put that at mid-2027](https://www.lacaribenanews.com/guyana-gas-to-energy-delay-gpl-losses-solar-2026/).

Jagdeo said power from the project would be sold to GPL at about US$0.05 a kilowatt-hour.

## Why did the project settle rather than arbitrate?

Time, on his account. The contractor claimed the access road was late and poor, and that extra site work was needed on the Gas-to-Energy project. The government disputed that, Jagdeo said. It considered arbitration after an award by the Dispute Adjudication Board.

Arbitration could have taken several more years, he said. Importing fuel to generate the equivalent of the 300MW the gas project is to supply could cost more than US$300 million a year.

## What has actually been contracted?

Two sections of the backbone, and an operator. Jagdeo named a G$422 million contract towards West Bank Demerara, about US$2.0 million. He named another of about G$160 million towards Kuru Kururu, about US$766,000.

Siemens has been contracted to operate and maintain the power plant under a long-term agreement. The government is close to an agreement with a United States company to operate the natural gas liquids facility.

## What should a Caribbean reader take from this?

That the constraint is moving from the plant to the pole.

A firm sizing a connection in Guyana is buying into a network carrying 231,000 customers against 184,000 in 2019, on lines its own Vice President describes as overloaded.

Against the US$4.8 billion named for that network, the contracts he named on Thursday were G$422 million and G$160 million. Neither the backbone nor the distribution programme was given a completion date.

He spoke at the same dinner about the currency that pays for the equipment. [The state supplies about US$2.5 billion of foreign currency to the market directly this year and is looking to more than double that next year](https://www.lacaribenanews.com/guyana-state-forex-supply-2-5-billion-double-imports-ten-billion-2026/). The association hosting him [named five industries to build from local raw materials](https://www.lacaribenanews.com/gmsa-five-industries-local-raw-materials-khan-apad-2026/).

### Title card, text equivalent

All figures on the title card, with their sources.

The panel sets the network cost against the generation it carries: transmission backbone US$2.3 billion, distribution US$2.5 billion, the two combined US$4.8 billion, and the Wales gas plant US$956 million. Sources: the Vice President's remarks of 26 November 2026 for the network, and La Caribeña News on the Wales financing for the plant.

The four figures in the bottom strip:

- 1,500 km: the length of distribution network to be upgraded, with its transformers. Source: the Vice President, 26 November 2026.
- 130MW: peak demand in 2019, the one figure every report of the speech agrees on. Source: the reports of 27 November 2026.
- US$0.23: the rate charged a kilowatt-hour, against generation at US$0.3456 this year. Source: the same.
- G$95 billion: the combined subsidy this year, electricity and capital, about US$455 million. Source: the Guyana Chronicle's report of the same remarks.

### Entities named in this report

- **Dr Bharrat Jagdeo** is Vice President of the Co-operative Republic of Guyana.
- **The Guyana Manufacturing and Services Association (GMSA)** hosted the dinner at which he spoke.
- **Guyana Power and Light (GPL)** is the national utility and buys the gas project's output.
- **Deodat Indar** is Minister of Public Utilities and gave the earlier demand figure.
- **The Gas-to-Energy project** at Wales is the 300MW development the transmission work is to carry.
- **The Dispute Adjudication Board** issued the award that preceded the negotiated settlement.
- **Siemens** holds the long-term operations and maintenance agreement for the power plant.

## Frequently asked questions

How much does Guyana say its electricity network needs?

About US$2.3 billion for the transmission backbone and US$2.5 billion for distribution, on the Vice President's figures of 26 November 2026\. The gas plant those wires will carry was approved at US$956 million.

What does the distribution money buy?

Replacement transformers and the upgrading of about 1,500 kilometres of network. Jagdeo said lines are overloaded and the system has no redundancy, so one damaged pole can cut supply over a wide area.

Do the reported demand figures agree?

No. Reports of the remarks agree on a 2019 base of 130MW and on 255MW of available capacity. On peak demand now they range from 216MW to above 260MW. On 13 November the Minister of Public Utilities put it close to 269MW against about 260MW operating. No official has published the underlying series.

What does it cost to hold the electricity rate?

Generation cost US$0.3456 a kilowatt-hour this year against US$0.23 charged. Jagdeo put this year's electricity subsidy at G$33 billion and the capital subsidy at G$62 billion, a combined G$95 billion, about US$455 million.

When is the gas plant due?

The single-cycle unit at the end of the first quarter of 2027, and the combined-cycle unit around June 2027.