# Guyana's Peak Demand Reached 269 Megawatts Against 260 Operating. The Powership It Wanted Sailed to Venezuela.
- URL: https://www.lacaribenanews.com/guyana-peak-demand-269-megawatts-powership-venezuela-christmas-2026/
- Published: 2026-11-13T16:20:58.000Z
- Updated: 2026-11-15T05:23:12.000Z
- Description: Minister Deodat Indar told Kaieteur News on Wednesday that peak demand has reached close to 269MW against roughly 260MW of operating sets. A third powership Guyana was seeking went to Venezuela. He says no company in Guyana has a megawatt to sell to the grid.
- Author: Theon Alleyne
- Tags: Guyana, Energy, Business, Infrastructure, Beat: energy-transition-tariffs, MSME: direct

**Quick summary:** Minister Deodat Indar told Kaieteur News on Wednesday that peak demand has reached close to 269MW against roughly 260MW of operating sets. A third powership Guyana was seeking went to Venezuela. He says no company in Guyana has a megawatt to sell to the grid.

By LCN Business Desk

Guyana's peak electricity demand has reached close to 269 megawatts. Its operating sets produce around 260\. That is the Minister of Public Utilities and Aviation, Deodat Indar, speaking to [Kaieteur News](https://kaieteurnewsonline.com/2026/11/12/govt-in-mad-scramble-to-find-20-mw-of-power-for-christmas/?ref=lacaribenanews.com) on Wednesday.

The vessel the country was pursuing to close that gap has been rented to Venezuela.

## What is the shortfall?

Nine megawatts at peak, and it is the peak that matters.

Indar gave both figures: "The peak demand went close to 269MW. We have operating sets around 260\. We are bringing back some of the sets that are in repairs, those in overhaul that went past their working hours, we're trying to get them back in for the Christmas season."

A deficit at peak is not a deficit all day. It bites in the hours a business is open. And it arrives in the weeks when retail, hospitality and cold storage draw hardest.

The grid has already shown what the margin looks like when it goes. [Georgetown went dark five days after the utility said it had enough power](https://www.lacaribenanews.com/gpl-blackout-news-conferences-interenergy-2026/), and [four of Guyana's ten regions lost supply on the morning of 30 October](https://www.lacaribenanews.com/guyana-four-regions-power-outage-royal-business-reception-30-october-2026/).

## What happened to the powership?

It went to Venezuela instead.

Guyana rents two powerships from a Turkish firm and was seeking a third, larger vessel. Indar confirmed it is not coming: "No. We don't have any powership coming. We have to seek some additional power. We found about 20 megawatts, and we are working with a company to bring it to Guyana."

He told Kaieteur the available powership has been rented to Venezuela.

## Can the shortfall be bought locally?

The minister says there is nothing to buy.

Indar put it without hedging: "Listen, let's not fool ourselves, there is nobody in Guyana that has a generator to sell one megawatt. If they have one, it's already bought out. There is none."

He said the same of the wider region, and of the market generally: "It is not, you know, there is no power available anywhere that you can go pick up at the shop. There's none available. If anybody can say that they have power available, it will be untrue, because we've been checking all over."

Those are the words of the minister who buys the power. For a firm weighing its own generation, the plant is not sitting on a yard anywhere. Anyone offering it should be asked hard questions.

## Is the 20 megawatts secured?

The minister has given no date.

Indar said a company will supply around 20 megawatts and that talks are active, with the Christmas season as the target: "We found a company that is going to give us 20 megawatts. We are in active discussion with them to see if we can get that in for the Christmas season."

He could not say how soon it could reach the national grid, Kaieteur reported, because discussions are continuing. The company has not been named.

## What is being done with the existing fleet?

Units in repair and overhaul are being brought back.

The minister described returning sets that are in repairs and others past their working hours in overhaul, and said the difficulty is sourcing parts from around the world. Parts delivery is a supply-chain lead time rather than a procurement decision, and it sets a floor on how fast the operating figure can move.

The relief the government has promised does not arrive this season either. The gas-to-energy plant at Wales is the structural answer. But the Prime Minister has said [the promised fifty per cent cut to bills waits on the plant running at full capacity](https://www.lacaribenanews.com/guyana-gas-to-energy-delay-gpl-losses-solar-2026/). Its contractor was [given a December date for first power in a May settlement that raised the contract 12.8 per cent](https://www.lacaribenanews.com/guyana-lindsayca-wales-97-million-settlement-first-power-deadline-2026/). The government has since approved more than US$100M more, on a sum the Prime Minister told Kaieteur News he could not recall.

## Why this matters to a business planning December

Because the gap is at peak and the replacement is undated.

A firm scheduling production, refrigeration or longer trading hours through December is planning against a known gap. The minister has put operating capacity below peak demand. The extra 20 megawatts is in discussion, not contracted. No powership is coming. No local supplier can sell a megawatt. Two things would close it. Parts arriving for units under overhaul, and an unnamed company delivering on an unstated date.

### The entities

\- **Deodat Indar** is Guyana's Minister of Public Utilities and Aviation. - **Venezuela** rented the powership Guyana was seeking. - **Kaieteur News** reported the minister's remarks on the sidelines of Parliament.

### What the title card says

\- Headline: Guyana's peak demand reached 269 megawatts against 260 operating, and the powership it wanted sailed to Venezuela. - Peak demand: close to 269MW. - Operating sets: around 260MW. - Additional power being sought: about 20 megawatts. - Powerships currently rented: two, from a Turkish firm. - Third powership: rented to Venezuela. - Megawatts available from a Guyanese supplier, per the minister: none. - Date for the 20 megawatts: none given by the minister.

## Frequently Asked Questions

What is Guyana's electricity shortfall?

Minister Deodat Indar said peak demand has reached close to 269MW while operating sets produce around 260MW.

Why is Guyana not getting the powership it wanted?

It was rented to Venezuela. Guyana currently rents two powerships from a Turkish firm and had been seeking a third, larger vessel.

Can Guyanese companies supply the shortfall?

The minister said no company in Guyana has a megawatt to sell to the grid, and that any already available is bought out.

When will the additional 20 megawatts arrive?

No date has been given. The minister said discussions with a company are active and the target is the Christmas season. The company has not been named.

What is being done with existing generating units?

Units in repair and in overhaul past their working hours are being returned to service, with parts sourced internationally.